Background: Bureau Valley Walnut Elementary School underwent a transformative redevelopment as part of a district-wide bond referendum, with MCP successfully spearheading the comprehensive effort and leading the 25+ member referendum committee.
Scale of the Project: Distinguished by its magnitude, the Walnut Elementary School project was three times larger than the simultaneous endeavor at Wyanet Elementary School, reflecting the ambitious scope of the construction initiative.
Scope of Impact: The project significantly impacted the majority of the existing school infrastructure, necessitating substantial upgrades to meet modern educational standards.
Mechanical and Electrical Overhaul: In response to inadequate and outdated existing systems, the project included a major HVAC and electrical upgrade. All-new mechanical rooftop units were installed, alongside a comprehensive enhancement of the electrical service, ensuring the school’s systems aligned with contemporary efficiency and safety standards.
Interior Renovations: Renovations extended beyond the technical aspects, encompassing the installation of new ceilings and lighting throughout the school. These enhancements not only modernized the environment but also contributed to an improved learning atmosphere for students and faculty.
Project Management Excellence: MCP demonstrated adept project management by overseeing two prime contractors, ensuring seamless coordination and execution of the HVAC and electrical upgrades.
Summer Timetable: To minimize disruptions to the academic calendar, all project work at Walnut Elementary School was successfully completed during the summer months. This strategic timeline allowed for the efficient implementation of the upgrades within a condensed timeframe.
Collaborative Approach: Situated 15 miles from Bureau Valley High School, another concurrent MCP-managed project, Walnut Elementary School benefitted from the utilization of the same dedicated project team—comprising a project manager and superintendent. This collaborative approach not only optimized efficiency but also resulted in substantial cost savings for the district.
Simultaneous Project Management: In a remarkable display of multitasking, MCP concurrently managed the HVAC and Electrical Upgrade project at Wyanet Elementary School during the same summer. Leveraging the same MCP project team, this simultaneous management further showcased MCP’s ability to handle complex projects efficiently.
The Bureau Valley Walnut Elementary School project stands as a testament to MCP’s capability to manage large-scale construction endeavors, deliver impactful upgrades, and navigate intricate logistical challenges while maintaining a commitment to excellence and cost-effectiveness.